Future Land Use & Text Amendment Applications
- Applications, Instructions and Forms
-
2012 Future Land
Use Application Form

-
2013 Future
Land Use Amendment Application Instructions

-
2013 Future Land Use Amendment Application Form (word)

-
2013 Text Amendment Application Instructions-Form (word)
-
Disclosure of Ownership Interests-Memo

-
Disclosure of Ownership Interests-Applicant
-
Disclosure of Ownership Interests-Property

- Fees:
- Traffic Pre-Application Review:
-
Applications must submit a portion of the traffic study and partial FLUA application to the Traffic Division for review 30 days (for Small Scale Amendments) and 60 days (for Large Scale Amendments) prior to the FLUA Application intake deadline. Approval of the traffic study must be obtained prior to intake for the amendment. Instructions are contained within the Future Land Use Application.
With the exception of the intake dates, all dates are tentative.
| 2012 Large Scale Schedule | ||||
| Activity | 12-1 | 12-2 | ||
| Private FLUA Intake | October 7, 2011 | February 3, 2012 | ||
| LPA Workshop | January 13, 2012 | May 11, 2012 | ||
| LPA Public Hearing | Feb. 10, 25 & Mar. 11 | June 8, 2012 | ||
| BCC Transmittal Hearing | March 28, 2012 | July 23,2012 | ||
| BCC Adoption Hearing | July 23, 2012 | October 2012 | ||
| Anticipated Effective Date | September 2012 | November 2012 | ||
| 2012 Small Scale Schedule | ||||
| Activity | 12-A | 12-B | 12-C | 12-D |
| Private FLUA Intake | Aug. 7, 2011 | Oct. 7, 2011 | Feb.3, 2012 | May 4, 2012 |
| 2013 Large Scale Schedule | |||
| Activity | 13-1 | 13-2 | |
| Private Text Intake | June 22, 2012 | Nov. 30, 2012 | |
| LPA Initiation | July 13, 2012 | Dec. 14, 2012 | |
| BCC Initiation | July 23, 2012 | January 2013 | |
| Private FLUA Intake | August 3, 2012 | February 1, 2013 | |
| LPA Workshop | October 12, 2012 | May 10, 2013 | |
| LPA Public Hearing | Nov. 9 & Dec. 14, 2012 | June 7 & 21, 2013 | |
| BCC Transmittal Hearing | January 2013 | July 2013 | |
| BCC Adoption Hearing | April 2013 | October 2013 | |
| Anticipated Effective Date | May 2013 | November 2013 | |
| 2013 Small Scale Schedule | ||||
| Activity | 13-A | 13-B | 13-C | 13-D |
| Private Text Intake | June 1, 2012 | Aug. 31, 2012 | Nov. 30, 2012 | Mar. 1. 2013 |
| Private FLUA Intake | Aug. 3, 2012 | Nov. 2, 2012 | Feb.1, 2013 | May 3, 2013 |